Dueall Construction

Resident Communication Program

Valhalla of Brandon Pointe · Painting and Stucco Restoration

OwnerValhalla of Brandon Pointe HOA
Property managerGreenacre Properties
EngineerBeryl Project Engineering, LLC
Schedule60 weeks · 2 Nov 2026 to 28 Dec 2027
Units590 across 87 buildings
StatusConcept — examples, subject to change
01

What the notice program does for this project

Beryl's specification does not set a resident notice rule. The obligation sits in the Florida Paints specification, and it runs through the owner: the contractor advises the owner of the areas where work is to be performed, with sufficient time for the owner to notify all occupants. This program is how Dueall meets that, and gives the Association and Greenacre enough lead to act on it.

87Building start notices, one per building
7Calendar days of lead on every one
590Units across the community
8Notice types in the set

Two specification lines drive the whole program. Florida Paints §4.3: the contractor will advise the owner of those areas in which work is to be performed, with sufficient time to permit the owner to notify all occupants. Florida Paints §4.2: the owner will make every effort to notify occupants to remove personal items, patio furniture and vehicles, and the contractor is relieved of responsibility for damage to property that was not moved. The notice is what makes that second clause work. Without a dated record of it, the relief does not hold.

The community hears from Dueall before it sees Dueall. The sequence opens at week 0, the week of 26 to 30 October 2026, with no one on the property. The pre-construction letter reaches all 590 units that week, and the first five building notices — buildings 1, 2, 3, 6 and 7, which start on 2 November — go with it on Thursday 29 October, three working days ahead. Play the site map from the beginning and that is what you see first: a quiet community, and notices going out, before a single crew arrives.
02

Cadence against the 60-week sequence

Notices do not go out at a steady rate. They come in clusters, because buildings start in clusters, each time crews free up and a new group opens. Across the 60 weeks, notices fall in 32 of the 62 weeks. The heaviest carry five, and no week carries more.

Busiest notice weeksNotices due
Week 0 — before mobilization5 building notices
Week 115 building notices
Week 205 building notices
Week 335 building notices
Week 435 building notices
Week 475 building notices
Week 505 building notices

The live schedule carries the full week-by-week list, and the schedule workbook has a Notice Log tab sorted by notice date with blank Delivered, Delivered by and Notes columns for whoever walks them.

The rule. Seven calendar days before the building's first working day. If that date lands on a weekend or an excluded holiday it rolls back to the previous working day. On this sequence no rollback is needed anywhere, so all 87 land on a clean 7-day lead.
03

Register and delivery volume by yard

Buildings, units and the notice window for each staging yard, in build order.

YardStaging areaBuildingsUnitsFirst noticeLast noticeYard open
1Main laydown & field office — clubhouse drive6382026-10-292026-12-14wk 1–61
2Barnstead Dr north parking court9642026-10-292027-02-22wk 1–21
3Interior drive elbow — central rows at the middle pond15862027-01-112027-05-21wk 11–34
4Pond Ridge Dr east drive221562027-03-192027-08-02wk 21–44
6Barnstead × Haverhill Ridge connector14922027-06-182027-11-01wk 34–57
5Pond Ridge Dr south — Valhalla Pond frontage171242027-08-272027-11-24wk 44–58
7Chatham Gate Dr cul-de-sac — detached southwest cluster4302027-11-302027-11-30wk 57–61
Total87590
04

The notice set

Eight notice types cover the whole job. Open any one below to read the full example wording — what a resident actually receives, not a description of it. The same eight are carried in the Inspection, Notice & Reporting document.

N-1

Pre-Construction Letter

Once, before mobilization  ·  Every unit, 590

Introduces the project, the 60-week window, working hours, the seven staging yards, and the two points of contact. It goes out in week 0, the week before mobilization, together with the first five building notices.

Once, before mobilizationAll 590 units
Concept
N-2

Building Start Notice

7 calendar days before each building starts  ·  The units in that building

The core notice. Names the building, the start and finish dates, the scope on that building, and what the resident has to move. 87 of these across the job, every one on a clean seven-day lead.

Seven calendar days before startThe units in that building · 87 of these
Concept
N-3

Staging Yard Opening Notice

At each yard opening, ahead of the first building  ·  Units served by that yard

Fencing, dumpster and laydown going in, plus any parking that comes out of use. Seven of these. Yard 1 opens once and stays for the full 60 weeks; the other six open and strike in sequence.

At each yard openingUnits served by that yard · 7 of these
Concept
N-4

Access, Water and Interior Work Advisory

At least 48 hours ahead  ·  Affected units

Any day a lanai, entry or hose bib is affected, and the three or four day span when a window comes out and the interior is made good. Beryl spec p.8 allows hose-bib use provided the bibs are restored to their prior condition.

At least 48 hours aheadAffected units
Concept
N-5

Stucco Installation Notice

2 working days ahead  ·  The units in that building

The three-coat cycle and the curing days in between, so residents understand why crews are wetting a wall on a day nothing else appears to be happening. Vehicles clear by 7:45 am on the application days. 74 of these.

Two working days aheadThe units in that building
Concept
N-6

Painting Notice

2 working days ahead  ·  The units in that building

The three paint days and what they ask of the resident: vehicles clear of the elevation being sprayed, windows and sliders closed, pets in. 87 of these.

Two working days aheadThe units in that building
Concept
N-7

Building Completion Notice

At the post-inspection  ·  The units in that building

Confirms the building is off the active list, what the punch list picked up, and the warranty that now applies: stucco 5 years, wood 2 years, metal 2 years. 87 of these.

At the post-inspectionThe units in that building · 87 of these
Concept
N-8

Saturday Work Notice

With the 48-hour Board request  ·  Units in the affected buildings

Only issued if a Saturday is approved. None is assumed anywhere in the 60-week sequence, so this notice may never be used.

With the 48-hour Board requestUnits in the affected buildings
Concept
05

The pre-construction packet and the interior work sheet

Two documents sit behind the notice set. The pre-construction packet is what gets handed out and walked through at the pre-construction meeting, before a single notice goes out. The interior work sheet answers the one question the notices cannot answer in a paragraph: how many days will people be inside my home.

Both are adapted from Dueall documents already in use on occupied exterior restoration work and rewritten against this project — 87 buildings, 590 units, 28,945 square feet of stucco and 117 windows, on townhomes with driveways and screen porches rather than a tower over a parking garage. Scope that does not apply here has been taken out rather than left in.
PC-1

Pre-Construction Meeting Packet

Once, at the pre-construction meeting · Board, Greenacre, Beryl and any resident attending

The whole job walked through in the order a resident will see it: what to move before the crews arrive, then access and protection, stucco removal, framing, the 117 windows, the barrier, three-coat stucco, paint, and close-out. Carries the drywall-damage and utility-strike instructions, the Monday-to-Friday contact hours and the project team block.

4 parts8 construction phasesHanded out and left with the Association
Concept
PC-2

Interior Work in Relation to the Exterior Schedule

Reference sheet · the basis for the N-4 access advisory

Per-unit day counts for window and framing work: four days for a corner or two-face unit, three for an interior unit with one face wall, because the drywall crew starts on the last day of the framing rather than after it. Also what the resident takes down, what Dueall brings, and how the days are set against the building's fifteen-working-day cycle.

2 unit types3 to 4 days per unitFeeds N-4
Concept
06

How a notice gets out the door

Schedule generates the date

Every building's notice date is fixed the moment its start date is set, at seven days back. Nothing is decided by hand.

Automatic · from the 60-week sequence

Superintendent confirms the week ahead

At the Friday look-ahead the superintendent confirms the buildings starting in the following week and releases those notices. A building that has slipped does not get a notice it cannot honour.

Site superintendent · every Friday

Greenacre and Beryl copied before the drop

The property manager and the engineer get the list before anything is delivered, so the office is never hearing about a building from a resident first.

To David Griffith and Nathan Polanco

Delivered to the door and logged

Hand delivered to each unit in the building. Logged against the Notice Log with date, time and who delivered it.

Site staff · seven days ahead

Confirmed at the pre-inspection

The pre-inspection on day one checks that the notice went out and that furniture and vehicles are clear. If they are not, that is recorded before a crew touches the building.

Owner's agent (Beryl) · INSP-02
07

What we need from the Owner and Engineer

From the Association and Greenacre Properties

From Beryl Project Engineering