Dueall Construction

PROJECT STAFFING GUIDE

Project Oversight Structure
VALHALLA OF BRANDON POINTE Painting & Stucco Restoration
RFP No. 55378
Page 1 of 5 · August 2026
Designated Estimator
Budgeting, change pricing and unit-cost input against Beryl items U2, U3 and U4. Prices any extra work before it starts.
Project Executive
Contract, change orders and the relationship with the Board and Beryl. Signs the pay applications.
Safety & Compliance
OSHA compliance across scaffold and ladder-jack work, and the daily site clean-down — grounds magneted, dumpsters covered and locked before leaving.
Project Manager
Owns the 60-week sequence, the yard rotation and the trade coverage. Single point of contact for Beryl on schedule and scope.
Project Coordinator
Permits, one per building, and the paperwork that gates payment: lien releases, AIA G702 and G703, and the closeout package.
Site Superintendent
Required by Beryl spec p.10 — an on-site full-time supervisor for the crews during working periods. Runs the two open work fronts, releases the weekly resident notices, and hosts the pre, mid and post inspections.
Field Engineer / QC
Daily quality-control field report to the Florida Paints representative and the owner’s representative (Florida Paints §10.6). Runs the moisture and substrate checks before every first coat.
Assistant Superintendent
Second set of eyes across the two live yards, so neither front is unsupervised while the other is being walked with the engineer.
Foreman — five, one per crew
Runs a building end to end, prep through closeout.
Crew — five, floating between two live yards
One crew takes one building start to finish. 87 buildings, 1,175 crew working days.
The staffing follows the sequence Because only two staging yards are live at a time, the site is never spread wider than one superintendent and one assistant can walk in a morning. Beryl spec p.10 requires an on-site full-time supervisor; that is a floor, not a plan. With 87 buildings, 590 units and 509 dated inspection events, the site carries a superintendent and an assistant so that one front is never unsupervised while the other is being walked with the engineer. Assignments are confirmed at award and reviewed with the Association before mobilization.
Direct Reporting Collaborative Support
Dueall Construction

THE CREW MODEL

Five Crews Against Two Work Fronts
VALHALLA OF BRANDON POINTE Painting & Stucco Restoration
RFP No. 55378
Page 2 of 5 · August 2026
5Crews, floating between the two live yards
2Work fronts open at any one time
7Staging yards, one of them permanent
1,175Crew working days across the job
1Full-time on-site supervisor, required by spec

A crew takes a building end to end: one day prep, ten days stucco repair on full-scope buildings, three days paint, one day closeout. Fifteen working days for a full-scope building, five for a paint-only — 74 full scope and 13 paint-only across the 87. Crews do not specialise by trade; they carry a building through, which is what makes per-building payment and per-building punch lists work.

CrewBuildingsWorking daysUnitsStucco SF
Crew 1182301205,132
Crew 2192551286,493
Crew 3162401125,356
Crew 4182301165,735
Crew 5162201146,229
Total871,17559028,945

Why five
crews

Four crews cannot beat 62.4 weeks under the two-front rule, tested across every one of the 5,040 possible yard orderings. Six finishes near 42 weeks but puts more of the community under scaffold at once. Five is what lands the job on 60 weeks.

How the yards
rotate

Yard 1 never closes. Field office, primary roll-offs, material and lifts sit there for all 60 weeks.
  • Every other yard opens only after an earlier yard’s last building is finished and struck
  • Three working days to set a yard up, two to strike it
  • Crews take the next building in the yard with the most work remaining
One crew, one building, one superintendent. Payment on this project runs per building, and so does the punch list. A building that has been through four different hands is a building nobody owns at closeout. Grouping the trades into a crew that carries a building from prep to punch list is what lets Dueall put a completed building in front of Beryl and the Board every few days, rather than a partly-finished community for fourteen months.
Dueall Construction

TRADE COVERAGE

Every Line of Scope, and Who Carries It
VALHALLA OF BRANDON POINTE Painting & Stucco Restoration
RFP No. 55378
Page 3 of 5 · August 2026

Every line of the scope is covered, and every line is covered the same way: by a crew that belongs to a building, working under one Dueall superintendent, on a sequence the Association and the Engineer can see a week ahead. Trade partners are prequalified, carry the insurance the Association’s requirements call for, and work to the same inspection forms Dueall’s own crews do.

TradeQuantity on this projectHow it is carriedGoverned by
Stucco repair28,945 SFSpecialist crews taking a building start to finish, so the same hands that open the wall close it.Beryl item 2.0 · INSP-C
Decorative banding3,669 LFCarried inside the stucco crew rather than let separately, so the band and the field wall are the same hand and the profile matches.Beryl item 2.0 · INSP-C
Foam features and shutters71 shuttersRemoved, tagged by unit, stored and re-installed by the crew that took them off.Beryl item 2.0 · INSP-E
Carpentry — sheathing, framing, fascia, soffit213 LF fascia · 270 LF soffitA carpentry crew working one step ahead of the lath, so nothing is covered before it is sound.Unit costs U2, U3, U4 · INSP-B
Windows117 openingsRemoved, flashed and re-set by the carpentry crew. Flashing and the window are one operation by one crew, never split between two.Beryl items 3A, 3B · INSP-D
Interior work at window returns117 returnsDrywall and texture one day, paint the next, following two days behind the window so the resident’s unit is a three or four day event, not an open one.Beryl item 3A · Notice N-4
Exterior painting724,912 SFPainting crews released building by building, only after the stucco repair has been signed off and the substrate has passed its moisture and pH check.Florida Paints §18 · INSP-E
Paint materialFull systemFlorida Paints, as named in the specification, with the manufacturer’s representative on site through the job and the ten-year material warranty running on it.Florida Paints specification
Scaffolding, netting and access89,088 SFErected and struck with the yard rotation, inspected and tagged by a competent person every morning. Ladder jacks reach the wall above a lanai, footed on grade or slab, so nothing bears on a resident’s porch roof.OSHA 1926 Subpart L · INSP-G
Gutters and downspouts36 LF / 50 LFRemoved, stored and re-installed to the unit they came off, by the building crew.Beryl item 2.0 · INSP-E
Site clean, waste and yard management7 yardsDueall self-perform, every day. Grounds magneted, dumpsters covered and locked, and the yard secured before the crews leave.INSP-G
Dueall Construction

RECONSTRUCTION EXPERTISE

How Our People Are Built for This Work
VALHALLA OF BRANDON POINTE Staffing Guide
Page 4 of 5
August 2026

Restoration is not new construction performed later. It is the work of correcting conditions that already exist, on occupied buildings, using assemblies that must be opened, diagnosed and rebuilt correctly the first time. At Valhalla that means 28,945 SF of stucco repair opened on 74 occupied buildings before 724,912 SF of coating goes over it. Dueall staffs and trains specifically for that discipline.

Restoration
Specialization

Our project leadership works in restoration and reconstruction as a full-time discipline, not as an occasional assignment.
  • Building envelope and water-intrusion remediation
  • Stucco, cladding, waterproofing and sealant systems
  • Structural and framing repair at existing conditions
  • Occupied-property phasing and resident coordination

Manufacturer
Relationships

We work directly with the manufacturers of the systems we install, and we bring them in early. On this project that is Florida Paints, named in the specification.
  • HP-1 pre-start meeting with the Florida Paints representative before any work
  • System selection matched to field conditions, not catalog assumptions
  • Substrate approval and detail review before the first coat
  • The ten-year material warranty protected through documented compliance

Manufacturer Rep
Field Validation

We routinely ask the manufacturer’s representative to inspect our work in place and validate our methods.
  • HP-5 mock-up and drawdown cards approved before any production painting
  • Independent confirmation that installation matches published requirements
  • Written field reports added to the project record
  • HP-8 manufacturer acceptance before final payment and retainage

In-House &
Engineer-Led Training

Traditional construction education programs do not address reconstruction and restoration. Dueall closes that gap directly.
  • In-house training programs developed for restoration work
  • Specialized training conducted with Engineers
  • Focused on identifying and correcting construction defects
  • Equally focused on preventing the same defects from recurring
What this means for Valhalla. The people assigned to this project have been trained for defect correction and prevention; the Florida Paints system will be reviewed with the manufacturer before the first coat; and the manufacturer’s representative will be on the property through the job to inspect and validate the work as it is installed. The Association and Beryl Project Engineering receive that documentation as part of the project record.
Dueall Construction

CONTACTS & REQUIREMENTS

Who to Call, and What We Need to Start
VALHALLA OF BRANDON POINTE Staffing Guide
Page 5 of 5
August 2026

Who to Contact

If you need…ContactRole on this project
Schedule, sequence, a building’s datesProject Manager, DueallEscalates to the Project Executive
Anything on site, todaySite Superintendent, DueallOn site full time during working periods, per Beryl spec p.10
Inspections, hold points, punch listsNathan Polanco, Beryl Project Engineering
reserve@beryleng.com · (813) 616-3301
Engineer of record
Site access, residents, parking, gatesDavid Griffith, Greenacre Properties
dgriffith@greenacre.com · (813) 293-8646
Property manager
Paint system, product substitution, field reportsScott Belko, Florida Paints
(407) 866-3015
Manufacturer representative
Pay applications, lien releases, closeoutProject Coordinator, DueallEscalates to the Project Executive
Beryl spec p.8: there can be no verbal agreements between the Contractor and the Association. Modifications are requested in writing by either party, and any extra work needs a written work order before it starts. Escalation runs Site Superintendent → Project Manager → Project Executive, and each step has authority to act — nothing waits for the next level to be available.

What We Need from the Owner and Engineer

From the Association
and Greenacre Properties

  • Bathrooms for the crews. Dueall has confirmed it will not use portable toilets on the property, in line with Beryl spec p.10. Across five crews and 60 weeks the location and walking distance from each live yard matter, so the facilities need naming yard by yard rather than in principle.
  • Electric is excluded by the specification, so crews run off their own generators. Hose-bib water is permitted provided the bibs are restored to their prior condition.
  • Background checks on anyone Dueall puts on the property, available on request for any worker on the job. The cost is already carried in the base bid, so the Association can ask for them at award rather than part way through.

From Beryl
Project Engineering

  • Inspection attendance on the scheduled dates. Five crews against two fronts means an inspection that slips a day pushes the building behind it, not just the one being inspected.
  • The mock-up building designated in time for approval on 5 November 2026, ahead of the first paint start.
  • The keyed site plan confirming building numbers, so the sequence, the notices and the inspection record all carry the same building identity from day one.