Dueall Construction

VALHALLA OF BRANDON POINTE

Concept Documents · Dueall Construction

Reference concept documents for the Valhalla of Brandon Pointe painting and stucco restoration project. Each one is drawn from Beryl Project Engineering's specification for RFP 55378 and the Florida Paints specification it incorporates. Select a document below to open it.

OwnerValhalla of Brandon Pointe HOA
EngineerBeryl Project Engineering, LLC
Property managerGreenacre Properties
Scope87 buildings · 590 units
Schedule60 weeks · 2 Nov 2026 to 28 Dec 2027
Issued26 August 2026
1

Concept Project Staffing

Who runs the job. The oversight structure, the five-crew model against two work fronts, how each trade is carried, and who to call for what.
Open document
2

Concept 60-Week Schedule

The live sequence. An aerial site map that plays week by week, a Gantt of all 87 buildings grouped by staging yard, and the resident notices running seven days ahead of the crews.
Open document
3

Concept Resident Communication

The notice program. Eight notice types, 87 building notices at a seven-day lead, delivery volume by yard, and how a notice gets out the door.
Open document
4

Concept Inspection & Reporting

How the work is inspected, and what the residents are told. Eight hold points, 509 dated inspection events, seven field forms written out line by line, the daily log, and the eight resident notices written out in full.
Open document
Concept status Every document in this set is a concept prepared for the Association and the Engineer of record, and is subject to change at their direction. Building numbers on the site map are provisional until Beryl confirms them against a keyed site plan. Two points in the bid documents remain open: the permit application window, and whether the community holds 86 or 87 buildings. The sanitary facilities question is settled — no portable toilets will be used on the property.